Nanaimo Terminal Avenue Utility Upgrades

Nanaimo Terminal Avenue Utility Upgrades

The City of Nanaimo BC has awarded Hazelwood Construction Services Inc. with the contract for the Terminal Avenue Utility Upgrades Project.

Award Date: 03/02/2017
Award Amount: $2,307,778.46 + Tax
Start Date: April 2017
Estimated Completion Date: October 31, 2017
Project Engineer: City of Nanaimo

The work involves the installation of approximately 300m of PVC DR14 watermain, 1400m of PVC DR35 sanitary sewer main, 675m of PVC DR35 storm sewer main, 7500m2 of asphalt pavement restoration and all other work incidental thereto as shown on the drawings.

`