PROJECT DETAILS

PROJECT TYPE
Current, Municipal Projects
REGION/LOCATION
Duncan, BC
START DATE
May, 2025
COMPLETION DATE
October, 2025

SCOPE OF THE WORK

  • Hot tap of 350 mm AC main c/w 850m of 200-300mm PVC watermain and appurtenances along with a significant concrete pad mounted KIOSK and valve assembly.
  • Minor electrical works for KIOSK.
  • In addition , installation of numerous 450-600mm HDPE culverts and headwalls.
  • Project includes full lane surface restoration of Boys Road.

Another exciting project for Cowichan Tribes, Chatwin Engineering and Hazelwood Construction.

`