The project scope is two main phases.

Approximately 48,000 square feet of the penstock steel inner liner for Units U5 and U6 will be stripped and recoated to restore its protective integrity and ensure long-term durability against corrosion and operational wear.

This is a three-stage process involving:

The supply of labour, materials, and equipment for the construction of sidewalks, bike lanes, and road rehabilitation on Esquimalt Road and Craigflower Road. The work includes underground utility renewals for storm and sanitary sewers using both open cut and trenchless methods, traffic signal upgrades and modifications, and the installation of rectangular rapid flashing beacons (RRFBs).

Replacement of deep (~12m) storm drain infrastructure at the intersection of Moss Street and Point Street in the City of Victoria.

Work includes – Shoring design and excavation to grade, removal of the existing damaged storm drain pipe cleaning, installation of new reinforced concrete pipe and manhole, replacement of adjacent underground infrastructure, and surface restoration.

Another exciting project for Cowichan Tribes, Chatwin Engineering and Hazelwood Construction.

Recoating the interior of the 10′ diameter penstock using fully automated technology. This is a 3-stage process involving high pressure washing, abrasive blasting and relining of the penstock. Access is gained through cutting in temporary access hatches and welding back on completion of the relining.

Work also includes the relining of the scroll case interior and the exterior of the turbine inlet valve. Structural repairs to the existing concrete and steel penstock supports is also to be completed.

Work will be completed over a 4-month period with reservoir levels monitored and pumped down as needed. Work also includes cleaning of the stator as park of the generator upgrade project happening concurrently.

Road safety improvements for motorists and pedestrians at the following intersections:
  • Willis Rd/Wallace Dr
  • Wallace Dr/West Saanich Rd
  • West Saanich Rd/Hartland Ave
Works include but not limited to:
  • >600lm of curb
  • >700m2 of sidewalk
  • ~4000m3 of common excavation
  • >2500m2 of asphaltic paving, traffic signaling, landscaping and various site improvements

Construction of proposed improvements along Peninsula Road between Sea Plane Base Road & Bay Street in Ucluelet.

The improvements generally include:

`