Upgrades to Ucluelet’s sanitary sewer system:
- Construction of a new sanitary lift station, involving excavating below sea level
- Upgrades to an existing lift station (new pumps & odour control etc)
- Replace existing sanitary sewers
- Install new sanitary forcemain
- All work done with no interruptions to existing sewer system
- Construction of new complete sewage lift station.
- Sanitary sewer and forcemain installation
- Decommissioning Existing Lift Station
- Lock-block retaining wall
- Temporary sewer bypass system
- Tie-ins to the existing water network and electrical work
- Recontouring of a 5 Ha mine waste stockpile followed by a 5 Ha, 1m thick, layered rock, soil and topsoil cap.
- Excavation and onsite relocation of 52,000 m3 of stockpiled mine waste.
- Grubbing and grinding 17 Ha of wood debris, respread over the site at the end of the job..
- Stripping stockpiling and relocation of 15,000m3 of topsoil.
- Drilling and blasting 29,000 m3 of rock, come with excavation and relocation onsite.
- 90,000 m3 of common excavation come with relocation onsite.
- 300mm, 450mm and 600mm culverts and concrete headwalls and 4000lm of ditching.
All of this work is being completed to prepare the groundwork for future roads in a proposed 130-lot subdivision on Snuneymuxw’s IR#3 .
Removing existing median between James Street and Beverly Street and replacing with new median combined with fencing and trees. Electrical modifications to both James and Beverly intersections.
Site clearing and leveling for the construction of a new 2,500m3 bolted steel water reservoir, utility works, retaining wall construction, mechanical and electrical works, surface works and landscaping restoration.
Install water main, sewer and storm drain including clean outs, perimeter drains and systems not directly entering the building but to within .8m to 1m of the building for those services that enter the building perimeter.
Other work to include ESC measures, protection fencing, demo and disposal of existing home & carriage house on site, removal of ex watermain, storm and sewer piping, clearing, grubbing & stripping of site, bulk excavation and backfill of building footprint. Supply of asphalt, line painting and concrete (wheel stops, curbing & flat surface concrete). Coordination with other subs (Mechanical, Electrical, Landscaping) including trenching, bedding and backfilling.
Site clearing, drilling and blasting, grading of private lot for the Nanaimo Brandt Dealership.
- Installation of water, storm and sewer.
- Installation of underground water storage tanks, septic tank and biofilter.
- Construction of a 6m-tall MSE retaining wall.
- Foundation prep for new dealership.
- Sidewalks, curbs, various concrete pads, paving.
The project scope is two main phases.
- Phase one is the construction of a 209,000m3 rock fill buttress to stabilize the existing lower slope of the landfill
- Phase two is the main landfill closure works which include site grading, installation of drainage items to collect leachate and runoff and geomembrane liner installation.
Approximately 48,000 square feet of the penstock steel inner liner for Units U5 and U6 will be stripped and recoated to restore its protective integrity and ensure long-term durability against corrosion and operational wear.
This is a three-stage process involving:
- High-pressure washing
- Abrasive blasting
- Relining of the penstock
The supply of labour, materials, and equipment for the construction of sidewalks, bike lanes, and road rehabilitation on Esquimalt Road and Craigflower Road. The work includes underground utility renewals for storm and sanitary sewers using both open cut and trenchless methods, traffic signal upgrades and modifications, and the installation of rectangular rapid flashing beacons (RRFBs).
