PROJECT DETAILS

PROJECT TYPE
Current Projects
REGION/LOCATION
Port Alberni, BC
START DATE
March 2026
COMPLETION DATE
July 2026

SCOPE OF THE WORK

Works for this project include supply and installation of 1,060m of 750mm diameter fused joint HDPE watermain along Franklin River Road to tie into the existing Bainbridge Treatment Plant. The project also involves fabrication of custom 750mm x 150mm tangential tees for air valve assemblies, plus complicated removals and sequencing for tie in works to the existing water treatment plant to minimize interruptions to water service.

`